School Bond Projects

2024 Mill & Bond - Investing in Excellence

Thanks to the support of our community, the Cherry Creek School District can continue to deliver excellence for our students, staff, and community.

The overwhelming support for the 2024 Mill and Bond helps to ensure high-quality teachers, innovation and in-demand career training, and safe, healthy schools for all students. The 2024 Bond is funding capital construction improvements across the district, with many of the projects underway. 

As the Laredo Middle School rebuild takes place in close proximity to Cherokee Trail, the information below highlights the project details.

Rebuilding and Modernizing Laredo Middle School

Laredo Middle School is the second oldest middle school in the Cherry Creek School District. Originally constructed in 1974, the current building has aged out of its useful life in terms of meeting the programmatic and student needs of today. The new school will have a larger footprint to support today’s educational needs, including specialized programs, brighter, flexible, and innovative learning spaces, and improve traffic flow and pedestrian safety around the school. 

Laredo MS Rebuild Renderings

Animated tour of the new Laredo Middle School to be built starting 2025

Estimated Cost:
$110 million

Construction Schedule:

  • September 2025: Construction begins
  • May 2027: Estimated completion
  • Summer 2027: Prepare new school for students to attend for 2027-28 school year
  • Fall 2027: Demolition of existing Laredo Middle School building
  • Spring 2028: Final landscaping work

Community Engagement:

  • Spring 2024: Master Planning process with outreach to students, staff, school/campus leadership, and broader community
  • May 2024: Community Open Houses (3)
  • August 2024: Feeder Bond Presentation
  • April 2025: Community Meeting